Construction Updates |
Summer 2008 -
*************************************************************************************************************************
October - 2008
*************************************************************************************************************************
July - 2009
Activity should begin mid July with construction fencing erected with visual consideration for our neighbors and safety of our students throughout the modernization project, expected to be completed by August 2011. We greatly appreciate the support of the Arcadia community for voting for Measure I and their support and patience as we experience temporary inconveniences throughout this most worthwhile project to enhance one of the best schools anywhere. Some of the components of the project will include state of the art technology in every classroom, new flooring in every classroom and the MPR, new building for the library and media center and student services including the office and health office, completely new expanded lunch pavilion area, new windows in many classrooms, enhanced fencing for Kindergarten play area, new fencing in many areas of campus with increased security, improved outdoor lighting, new expanded drainage system and electrical and technology applications, new landscaping, and more.
**************************************************************************************************************************
**************************************************************************************************************************
October 30, 2009
Abatement and demolition for rooms 14 – 17 is completed, painting and flooring replacement has begun. Rooms 14 – 17 are projected to be completed on December 5. The first phase of the cement foundation work will be poured for the Student Services Offices, Library and Computer lab Saturday, October 31.
**************************************************************************************************************************
November 6, 2009
Electrical and painting are completed, windows and floor replacement are underway in rooms 14-17. Rooms 14 – 17 and 18-21 are moving on Friday, December 5. The first phase of the cement foundation work was poured and slab work, phase two, will be poured soon for the Student Services Offices, Library and Computer Lab. Be watching for steel columns to be installed all next week! We are 24% complete.
**************************************************************************************************************************
November 13, 2009
It was great fun having our whole student body and staff sign a crossbeam for the new Student Services building! Each will be an integral part of Highland Oaks School forever. Electrical and painting are completed in rooms 14-17. Carpet and linoleum will be completed Nov. 18 and windows and technology installation on Nov. 25. Rooms 14 – 17 and 18-21 are moving on Friday, December 5. The first phase of the cement foundation work was poured, steel work will be completed Nov. 20, and slab work, phase two, will be poured November 21 for the Student Services Offices, Library and Computer Lab. We are 26% complete.
**************************************************************************************************************************
November 20, 2009
Carpet and linoleum has been completed in rooms 14-17 and windows and technology installation will be completed on Nov. 25. Rooms 14 – 17 and 18-21 are moving on Friday, December 5. The moving meeting for them is being set up for after school on December 1. The first phase of the cement foundation work and steel work have been completed and slab work on Saturday for the Student Services Offices, Library and Computer Lab.
**************************************************************************************************************************
November 25, 2009
The week of November 30 will bring final touches and clean up to rooms 14-17 with moving scheduled for Friday, December 4. The moving meeting for rooms 18-21 is being set up for after school on December 1. Cement foundation work, steel work and the slab have been completed for the Student Services Offices, Library and Computer Lab (41% completed). Wood framing is scheduled through December 11.
**************************************************************************************************************************
December 2009
The week of December 7 will bring abatement and demolition to rooms 18-21. The Student Services Offices, Library and Computer Lab (46% completed) have wood framing work scheduled through December 24.